Construction · General contracting · Construction management Project controls built in CareersMediaPartnershipsProject map
Healthcare · 2025

Trauma and Surgical Tower Addition

Twenty-four operating rooms, a trauma unit and a rooftop helipad, stacked against a hospital that kept treating patients on the other side of the wall.

Owner
Confidential
Location
U.S.
Our role
Construction manager at-risk
Delivery
CM at-risk
Scale
420,000 SF
Completed
2025
The brief

An eleven-story trauma and surgical tower built against a hospital that never closed, with 24 operating rooms, a rooftop helipad and every tie-in made around live patient care.

The new tower had to connect to the existing hospital on six floors, share its central plant and keep the emergency department open every hour of the job. Utility shutdowns, infection control barriers and noise near patient floors all had to be negotiated with clinical leaders. Imaging equipment, surgical lights and air handlers carried long lead times, and the hospital had already scheduled staff training and its first surgical cases for a fixed opening week.

How we built it

The approach.

  1. 01

    Shutdowns planned like surgery

    Every tie-in to the live hospital had a written plan, a rehearsal and a backout step, signed by facilities and clinical leaders before work began.

  2. 02

    Long-lead equipment on the schedule

    Imaging, surgical booms and air handlers were tracked as schedule activities with fabrication milestones, so a late shop drawing showed up weeks before it threatened a room.

  3. 03

    Weekly look-aheads with the owner

    Three-week look-aheads showed the hospital which decisions were due, which rooms were under pressure and what each delay would push downstream.

  4. 04

    Rooms turned over in order

    Operating rooms were commissioned and cleaned in the order the surgical staff needed them, so training started while the last floors were finished.

The outcome.

24Operating rooms delivered
38Live tie-ins with no unplanned outage
0Hours the emergency department closed
3-weekLook-ahead shared with the owner every week

“A shutdown on the hospital side is not our decision alone. We showed the clinical team the plan, the backout and the clock, and they told us when.”

Project executive, Jacob Wiseman
Healthcare

Planning something like this?

Send us your scope, target date and biggest concern. A senior Jacob Wiseman lead will read it personally.