Construction · General contracting · Construction management Project controls built in CareersMediaPartnershipsProject map
Student Housing · 2024

Residence Halls and Dining Commons

Two residence halls and a dining commons for 1,150 first-year students, delivered design-build against a move-in weekend that cannot move.

Owner
Confidential
Location
U.S.
Our role
Design-build contractor
Delivery
Design-build
Scale
1,150 beds
Completed
2024
The brief

Two residence halls and a dining commons for 1,150 first-year students, delivered design-build against a move-in weekend that no university can postpone.

The university needed beds for a growing first-year class and a dining hall to replace one that was past its life. Move-in weekend was fixed, and students had already been assigned rooms. The site sat in the middle of an active campus, with pedestrian routes, events and the existing dining hall all running during construction.

How we built it

The approach.

  1. 01

    Design-build to a hard date

    Design was completed in packages so foundations and structure could start while interiors were still being drawn.

  2. 02

    Repetition planned on purpose

    Room layouts were standardized so trades could move room to room at a steady rate, tracked floor by floor.

  3. 03

    Kitchen equipment as long lead

    Food service equipment and hoods were bought early and scheduled for install, startup and health inspection.

  4. 04

    Move-in rehearsed

    Housing staff ran a check-in rehearsal in the finished buildings a week before students arrived.

The outcome.

1,150Beds
2Residence halls
1Dining commons
On dateMove-in weekend

“Twelve hundred families had already booked hotel rooms for move-in. That was our completion date.”

Design-build manager, Jacob Wiseman
Student Housing

Planning something like this?

Send us your scope, target date and biggest concern. A senior Jacob Wiseman lead will read it personally.