Renewable Fuels Processing Facility
A renewable diesel unit built on an existing refinery site, with every tie-in made during a turnaround that could not run long.
- Owner
- Confidential
- Location
- U.S.
- Our role
- EPC contractor
- Delivery
- EPC
- Scale
- 1.2 miles of pipe rack
- Completed
- 2025
A processing unit converting an existing refinery site to renewable diesel, with new pipe racks, tanks and tie-ins made during a planned turnaround that could not run long.
The owner was converting part of an operating refinery to renewable diesel. New reactors, tanks and more than a mile of pipe rack had to be built beside live units, with hot work permits, gas monitoring and strict safety rules every day. Final tie-ins could only happen during a planned turnaround, and every day of overrun meant lost production across the site.
The approach.

- 01
Modules built off site
Pipe rack and equipment modules were fabricated off site and set in planned lifts, reducing work beside live units.
- 02
Turnaround scope frozen early
Tie-in scope was frozen months ahead, with every weld, valve and test package ready before the units came down.
- 03
Hour-by-hour turnaround schedule
The turnaround ran on an hourly schedule with shift reports, so the owner saw progress and pressure points every twelve hours.
- 04
Systems turned over for startup
Each system was tested, documented and handed to operations in startup order.
The outcome.
“In a turnaround every hour has a cost on the other side of the fence. We planned the work to the hour and reported it every shift.”
Turnaround manager, Jacob Wiseman




Planning something like this?
Send us your scope, target date and biggest concern. A senior Jacob Wiseman lead will read it personally.